Overview

Environmental Impact Statement (EIS)

Flushing Bay Promenade Improvements

Port Authority Planning Studies

Environmental Impact Statement (EIS)

  • The Federal Aviation Administration (FAA) is preparing an EIS for the LaGuardia Airport Access Improvement Project to evaluate the potential impacts of the Port Authority’s proposed AirTrain LGA project and to identify measures that may mitigate the effects of the proposed project.
  • The FAA is the lead federal agency for the preparation of the EIS, with involvement from 16 other federal, state, and local agencies as cooperating and participating agencies.
  • The EIS will analyze and evaluate the potential direct, indirect, and cumulative environmental impacts that may result from the proposed project. This would include but not be limited to analysis in categories such as air quality, visual effects, noise, traffic, socioeconomics, natural resources, historical/cultural resources, land use, and others.
  • Stakeholder and community involvement will occur throughout the duration of the EIS. At the outset of the EIS, the scoping process included a public comment period and public meetings held in June 2019. Public information sessions were held in January 2020 to share results of the FAA’s alternatives analysis and to provide updates on the EIS schedule and process. There will be a public comment period and workshops and hearings in the third/fourth quarter of 2020 following the FAA’s issuance of the Draft EIS in August 2020.
  • The FAA has established a project website to share information and keep the public and stakeholders apprised of the progress of the EIS process, which can be accessed at https://www.lgaaccesseis.com/. Furthermore, individuals can subscribe for project updates at https://www.lgaaccesseis.com/subscribe

 

 

Rendering of New LGA Proposed Airtrain Platform Central Hall

 

Progress to Date:

  • July 2015 – Announcement of Airport Advisory Panel Recommendations for LGA
  • February 2017 – Phase I LGA Air Train Planning Authorization approved by PA Board
  • November 2017 – Phase II LGA Air Train Planning Authorization approved by PA Board
  • June 2018 – New York State Legislature defines the potential corridor for Air Train project
  • October 2018 – EIS begins with an RFP for consultant to work with FAA during environmental review
  • May 2019 – FAA issues Notice of Intent for EIS
  • October 2019 – LGA AirTrain receives PA Board Project Authorization of $2.05 Billion
  • December 2019 – Port Authority issues Program Briefing Book
  • January 2020 – FAA hosts public workshops on alternatives
  • August 21, 2020 – FAA issues Notice of Availability of the Draft EIS

For additional information on the EIS please visit lgaaccesseis.com/

Collaborating Agencies

Footer

Redevelopment

  • About the Project
  • Explore The New LGA
  • In The Community
  • Job Opportunities
  • Contracting Opportunities
  • News & Media
  • Contact
  • FAQ
  • Privacy Policy
  • LaguardiaAirport.com

Affiliates

New York State


The Port Authority of New York and New Jersey

Follow Us

  • Facebook
  • Twitter
  • Instagram